El Paso, TX

Netsync Cabling & AP Installation East Campus

End User: Netsync

Contract Number:P5301231

Time Frame: 09/03/2024 – 02/03/2025 

Value:$161,578.00

Scope of work:

Access Communications Group completed 153 New Access Point installations and relocated 43 existing ones at THOP East Medical Center, running and terminating 143 Category 6A Cable Runs as needed. Additionally, 168 Access Points were replaced, and all necessary reprogramming and resynchronization were performed. ACG ensured compliance with installation procedures, providing fireproofing, labeling, and cable management. Necessary Cat6A patch panels and horizontal cable managers were installed. Furthermore, Access Points were swapped at Edgemere and MOB locations to optimize network infrastructure.